Plant Overview

Plant

Taichung Gas 3&4, like Taichung Gas 1&2, are fuel-oil gas turbine units at Taichung Power Plant's site in Longjing District, Taichung City, generally used for peak or reserve dispatch.

Taichung Gas3&4 are sister units to Gas1&2, built in the same first construction phase and commissioned in 1990, each also rated at around 70MW. These four gas turbines were the plant's earliest units, and as coal-fired units are retired and new gas capacity added, they continue to serve as flexible dispatch resources.

台中Gas3&4 (Fuel Oil) currently reports a net generation of 0 MW across 1 unit(s), against an installed capacity of 140 MW (0% utilization).

Fuel-oil and diesel units can start up quickly but have a high fuel cost, so they mainly serve as peaking or emergency reserve capacity. They typically run few hours per year, coming online more often only when system reserve margins are tight or other units are down for maintenance or repairs.

Fuel oil was an important peaking source before gas infrastructure became widespread. As LNG terminals and gas units have come online, its share has shrunk substantially, and it now mainly serves as system reserve and peak-support capacity.

Overlay Comparison

Compare load curves and daily peak trends across periods; unlocks automatically once enough data accumulates.

One sample every 10 minutes, showing generation over the last 24 hours. The dashed line is the prior 24-hour period (same time yesterday) for day-over-day comparison.

Unit Details

UnitFuel TypeCapacityNet GenerationUtilizationNote
台中Gas3&4Fuel Oil140 MW0 MW0%

Frequently Asked Questions

FAQ

台中Gas3&4 is classified under Fuel Oil in Taipower's open dataset, currently reporting 1 unit(s): 台中Gas3&4.