日月潭水庫

ID: 20502CentralOff-stream Reservoir

Real-time conditions and historical storage trends

Observed at: 09/18/2026 12:00Daily operation date: 09/17/2026 00:00

Source: Water Resources Agency Reservoir Conditions and Daily Reservoir Operations datasets

💡 Operational Notes & FAQ

日月潭水庫

Functions as a massive water battery: water is released downstream during peak hours and pumped back overnight during off-peak hours.

Storage ratioNormal Storage
95.9%
▲ +1.3% (vs Yesterday)— 0.0% (1 hr)

Effective storage: 12,319.1 10k m³ · Effective capacity: 12,846.1 10k m³

日月潭水庫 real-time hydraulic engineering cross-section日月潭水庫 real-time storage ratio is 95.9%.

Real-time Hydraulic Briefing

Synthesized water storage and flow dynamics

Current water storage for 日月潭水庫 is at 95.9% with a water level elevation of 747.7 m. Storage is up 1.3% compared to yesterday at the same time. Primary water supply covers Daguan and Mingtan Pumped-Storage Power Plants & downstream irrigation.

日月潭水庫 (ID: 20502) is an official Off-stream Reservoir situated in the Zhuoshui River System Diversion, operated and managed by Taiwan Power Company. In operation since 1934, this facility serves as a vital strategic pillar in Taiwan's regional water grid and flood mitigation network.

According to the latest observation, its effective water storage is approximately 12,319.1 (10k m³), with a storage ratio of 95.9% and a real-time water level elevation of 747.7 meters.

Primary functional purposes include Pumped-storage & Hydroelectric Power, Tourism, Downstream Irrigation, with key regional supply coverage extending across Daguan and Mingtan Pumped-Storage Power Plants & downstream irrigation.

Primary Supply Area:Daguan and Mingtan Pumped-Storage Power Plants & downstream irrigation
Pumped-storage & Hydroelectric PowerTourismDownstream Irrigation

Effective storage

12,319.1 10k m³

▲ +160.3 10k m³ (vs Yesterday)

Water level

747.7 m

▲ +0.2 m (vs Yesterday)

Inflow

N/A

Total outflow

N/A

Effective capacity

12,846.1 10k m³

Net Flow Balance

日月潭水庫 · Real-time hydrological balance and storage dispatch analysis

Inflow (Qin)
N/AUpstream catchment runoff inflow rate
Total outflow (Qout)
N/AGate release and flood desilting rate
Net Flow Balance (ΔQ)
N/AOfficial real-time inflow/outflow telemetry unavailable

24 小時水文吞吐平衡走勢

雙向對稱流量觀測(上方為上游入流,下方為大壩放流,穿梭折線為淨出入差額)

Discharge Gates & Facilities

Real-time telemetry for spillways, drainage tunnels, desilting tunnels, and power outlets.

All discharge gates closed (No flood release)
Spillway outflowMain spillway gate release or crest free overflow
N/A
24h 待命常閉
N/A
Power outletHydroelectric turbine power generation discharge
N/A
24h 待命常閉
N/A
Desilting tunnelBottom desilting and sediment bypass tunnel
N/A
24h 待命常閉
N/A
Drainage tunnelDedicated flood diversion tunnel release
N/A
24h 待命常閉
N/A
Water drawMunicipal water, industrial, or irrigation draw
N/A
24h 待命常閉
N/A
Other outflowEcological baseflow or auxiliary facility release
N/A
24h 待命常閉
N/A

Historical Storage Trends

View historical storage percentage and water volume trends over time.

Reservoir Specifications · Geographic Location

日月潭水庫 · Engineering profile and geospatial information

Managing AgencyTaiwan Power Company
Responsible for facility operation and flood dispatch
Facility TypeOff-stream Reservoir
Dam structure and engineering classification
River SystemZhuoshui River System Diversion
Primary catchment river basin and hydrological system
Effective capacity12,846.1 10k m³
Maximum designed water storage capacity of the dam
Year Completed193492 yrs in operation
Long-term water supply security and flood resilience
Geographic Location
23.8569°N, 120.9161°E南投縣 · 魚池鄉

Check real-time conditions and historical trends for other facilities in the same region.

Frequently Asked Questions

日月潭水庫 · Key insights into reservoir metrics, release mechanisms, and facility operations

FAQ

Functions as a massive water battery: water is released downstream during peak hours and pumped back overnight during off-peak hours.